Bronllys Hospital, Powys
Implementation & use |
|
| Management | Powys Local Health Board |
| Installation | Dulas Ltd |
| Aims | 1. To contribute to Powys, UK and National CO2 reduction targets by replacing fossil fuels with
renewables |
Technical specification |
|
| Technology | 485 Kyocera KC125-2 modules |
| Inverter | 8 Fronius IG60, 4 Fronius IG15, 2 Fronius IG30, 1 Fronius IG40 |
The story
The construction phase took three months throughout winter 2004/2005.
The installation has raised awareness of energy conservation issues amongst the staff and other hospital users. Many other Health Trusts have expressed an interest in the project and are now considering similar installations.